When is 0.6 feature freeze?

Hi @redshiftzero,

In the 0.6 milestone it says the feature freeze and the string freeze are March 6th for a realease March 13th. I kind of remember it was suggested to make Q/A two weeks this time around because there are significant changes, which would place the freeze February 27th. Did I miss anything ?

Cheers

1 Like

Thanks for ping, so after a bit of discussion today, a consensus was to feature freeze and branch off February 27th to begin QA, allowing for bugfixes and test improvements in that two week period. The string freeze is still March 6th. Let me know if you think there are any unforeseen issues there. Erik/eloquence updated the milestone for now :sunny: